The Ho Chi Minh City People's Committee approved the city's central square and administrative center project under a public-private partnership scheme using a build-transfer (BT) contract.
The project will be built in An Khanh Ward and will require nearly 47 hectares of land. Its four components have a combined estimated investment of nearly VND30 trillion.
The four project components
The first component covers technical infrastructure, auxiliary works and an underground parking facility in the landscape park area. Its investment is estimated at more than VND3.77 trillion. The second component, the city administrative center, has an estimated investment of more than VND18.2 trillion.
The third component, a conference and performance center, has a preliminary investment of VND6.856 trillion. The fourth, the city's central square, was approved earlier with funding of more than VND733 billion.
The landscape park will cover more than 33 hectares. It will include a 50,000-square-meter underground parking facility, about 22 hectares of parkland and auxiliary works.
The project will also renovate and widen a 1.13-kilometer section of To Huu Street within the planning boundary. It will build a 640-meter parallel service road along Mai Chi Tho Street and a 540-meter road along Nguyen Co Thach Street.

Administrative center and square specifications
The administrative center is designed with two basement levels, 30 above-ground floors and a technical roof level. Its height to the roof peak will be nearly 170 meters. The site will cover more than 78,300 square meters, with a total construction floor area of 389,100 square meters.
The conference and performance center is expected to seat about 2,000 people. The central square will cover 119,000 square meters. It will accommodate about 268,000 people during the main political festival and 500,000 during a cultural festival.
According to the Ho Chi Minh City People's Committee, the complex is intended to create a centralized administrative center and reduce the dispersion of government offices. It will also add green and public spaces for large-scale events, festivals and community activities.
Funding and schedule
The project will use a BT contract. Payment will combine land resources and the city budget, with land prioritized for payment.
The investor will be Sun Saigon Investment and Development Co., Ltd. The Management Board of Investment and Construction of Civil and Industrial Works will sign, manage and implement the BT contract.
Under the approved schedule, 2026 is allocated to project preparation, preparation and appraisal of the feasibility study, and approval. Some works may start alongside negotiations and completion of the BT contract, but only after all legal conditions are met.
The implementation stage is expected to run from 2026 to 2027. It includes design and cost-estimate preparation and appraisal, contractor selection, construction, supervision, acceptance and handover for use.
From 2027 to 2028, the project will be completed, accounts will be settled, the works will be covered by warranties and related documents will be handed over.