On November 18, the Gia Lai Project Management Board for Transport and Civil Works said an inspection had found cracks in 139 homes along ĐH26 Road. The damage was linked to soil transport for the Quy Nhon – Pleiku expressway project.

Local authorities had previously counted 99 affected households. The latest inspection found cracks in 139 homes.
Most of the cracks are hairline patterns on walls and have not seriously affected the main structures. Some older houses have more cracks.
After the inspection was completed, the unit said it would need about 10 days to prepare a compensation plan. The plan is expected to be completed by November 28 and sent to the commune for notification to owners of damaged homes. Compensation payments will be made after residents agree.
Road repairs and a proposal to reroute empty trucks
To reduce the impact on residents, the project owner ordered contractors to water the road to limit dust according to specified shifts, times and areas. Contractors were also told to repair subsided and damaged sections of the road and shoulders regularly.

Because of the rain, damaged spots are currently being patched temporarily with crushed-stone aggregate. When the weather is dry, the unit will lay asphalt to maintain traffic safety. Nineteen passing bays have also been arranged along ĐH26 Road so residents can make way for trucks.
The project owner is also proposing a new route for empty trucks to reduce pressure on the road. The unit has worked with the Department of Agriculture and Environment and an irrigation company, proposing that empty trucks use National Highway 19, cross the Van Phong weir bridge and then travel to the borrow pit instead of using ĐH26 in the opposite direction as they do now.
The proposal is awaiting consideration and approval in principle from the Gia Lai People's Committee.
Earlier, frequent trips by soil trucks serving the expressway project along ĐH26 near Phu Lac hamlet in Binh An Commune angered residents. They reported cracks in their homes, a deteriorating road, dust and potential traffic safety risks.
Residents said the trucks operated continuously day and night, causing noise, dust and vibrations in their homes. ĐH26 Road is relatively narrow, but heavy vehicles use it frequently.
In response, residents blocked the road several times and stopped soil trucks from passing, leaving dozens of vehicles lined up along the route.
Le Van Nguyen, 80, of Phu Lac hamlet, said residents supported the Quy Nhon – Pleiku expressway project. He said he hoped the project owner and contractors would soon address the effects of material transport and protect residents' health and safety.
The Quy Nhon – Pleiku expressway will be about 125 km long. It is planned as a four-lane road with a 24.75-meter roadbed and a design speed of 100 kph. The project has a total investment of more than VND43.7 trillion and is scheduled for 2025–2029.
Sources: Thanh Niên