Vietnam sets deadlines to review Long Thanh Airport readiness

Vietnam's Construction Ministry ordered ACV to review Long Thanh Airport's readiness and report by November 15. The airport is planned to open on December 24.

Long Thanh Airport under construction in Vietnam
Photo: Dân Trí

Vietnam's Construction Ministry sent a document to the Civil Aviation Authority of Vietnam and Airports Corporation of Vietnam, known as ACV, on preparations to put the first phase of Long Thanh International Airport into operation.

ACV was asked to carry out all requirements in the directive issued by Standing Deputy Prime Minister Pham Gia Tuc in Government Office document No. 11272 dated November 5.

Full review of airport readiness

ACV must urgently work with the Civil Aviation Authority of Vietnam, relevant ministries, agencies and local authorities to prepare an operating plan for the first phase of Long Thanh Airport. The preparations must ensure security and safety, remain feasible, meet the government's requirements and stay on schedule.

One of the main tasks is to review progress on the completion of work packages and construction items, as well as the conditions and preparation plan needed to put the airport into operation.

The construction schedule must be coordinated with acceptance procedures, completion of legal formalities, permits and specialized approvals required for civil aviation. These matters must be linked to the results of the Operational Readiness and Airport Transfer, or ORAT, program and the plan for actual operations.

After the review, ACV must submit a report to the Construction Ministry and the Civil Aviation Authority of Vietnam by November 15.

The Civil Aviation Authority of Vietnam was asked to fully exercise its powers and responsibilities under civil aviation law and continue its role as the standing body of the steering committee preparing Long Thanh International Airport for operation. It must also coordinate with and support ACV and relevant agencies in preparing the conditions and documents required to open the airport.

The authority must also review and assess the operating plan submitted by ACV. It must send the results to the Construction Ministry by November 18, so the ministry can hold a review meeting on preparations for airport operations in November 2026.

Transport projects under review

The Construction Ministry also ordered an urgent review of transport projects connected to the airport to ensure convenient access after Long Thanh begins operating.

The Department of Construction Investment Economics and Management and the Vietnam Roads Administration were assigned to work with relevant agencies to inspect and accelerate highway projects, as well as upgrades to national and provincial roads connected to Long Thanh Airport.

The goal is to keep traffic moving smoothly and prevent congestion when the airport begins operating. The agencies must report on the connection and operating capacity to the Construction Ministry by November 16.

Earlier, ACV reported to the Civil Aviation Authority of Vietnam that it planned to begin operating Long Thanh International Airport at 12:00 a.m. on December 24, local time. ACV also told airlines to prepare suitable operating plans in advance and coordinate with ACV and relevant agencies during preparations, while meeting the deadline and complying with state regulations.

Sources: Dân Trí