Ho Chi Minh City - Long Thanh Expressway expansion: XL01 package reaches 80% completion

Work on the XL01 package of the Ho Chi Minh City - Long Thanh Expressway expansion is about 80% complete. Nearly 900 people and more than 200 machines are on site.

Construction of Long Thanh Bridge on the expanded Ho Chi Minh City — Long Thanh Expressway
Thanh Niên / To Chi Hung

Hundreds of engineers and workers are active at the XL01 construction site of the Ho Chi Minh City - Long Thanh Expressway expansion project.

The XL01 package aims to connect Long Thanh Bridge by the end of December 2026 and complete the package in March 2027. It is part of the nearly 10-kilometre expansion project for the Ho Chi Minh City - Long Thanh Expressway, valued at nearly VND 5.6 trillion. The work is being carried out by a contractor consortium led by Deo Ca Group.

Construction of the package began in August 2025, but the full site was not handed over until June 2026. This significantly shortened the construction period.

Workers at the Ho Chi Minh City - Long Thanh Expressway expansion site

To meet the schedule, the contractor consortium has mobilised nearly 900 people and more than 200 machines and pieces of equipment. Work is organised across 33 teams: 22 on viaducts, 5 on Long Thanh Bridge and 6 on beam casting.

The teams are working at the same time and continuously to complete the remaining work as planned. Workers are using every hour and day to make up for the shortened construction period.

Long Thanh Bridge construction site viewed from above

Nguyen Ngoc Lam, executive director of the XL01 package, said overall progress had reached about 80%. Basic ground treatment for the road section is complete, bored piles for the viaducts have been finished and the substructure is nearly 98% complete. Beam installation is 92% complete, the first stage of deck slab construction is 81% complete and the barriers are 43% complete.

On the main Long Thanh Bridge, the contractor has completed the D2000 bored piles, pile caps, pier shafts and K0 pier heads. Balanced cantilever casting has begun on 8 of 85 segments, in line with the planned bridge connection schedule.

The viaducts and Song Tac Bridge are scheduled for completion in 11.1026, allowing traffic to be diverted so the old bridge can be repaired.

Once completed, the Ho Chi Minh City - Long Thanh Expressway expansion is expected to increase capacity, reduce pressure on the existing route and improve connections between Ho Chi Minh City, Long Thanh International Airport, Dong Nai and the economic centres of southeastern Vietnam.

The 55-kilometre Ho Chi Minh City - Long Thanh - Dau Giay Expressway runs through Ho Chi Minh City and Dong Nai and opened in 2015. Total investment was VND 20.6 trillion.

After more than 10 years of operation, the expressway has often experienced congestion because of heavy traffic, especially on weekends, public holidays and Tet.

Sources: Thanh Niên