From November 10 to 30, the first lane of the Ho Chi Minh City–Trung Lương–Mỹ Thuận Expressway, toward Tây Ninh, will be closed to traffic from 10 p.m. to 6 a.m. the following morning. The restriction is for bridge-beam installation.
On November 10, the management unit for the expressway expansion project said the one-lane closure would support the transport, staging and lifting of Super-T beams at construction package XL03 in Tây Ninh Province.
The work area runs from Km35+625 to Km38+900. The contractor will install Super-T beams across nine spans, from pier T60 to pier T69, on the left side of the expressway.
The first lane toward Tây Ninh will be used to stage cranes and beam-transport vehicles and to carry out the lifting and installation work. Vehicles will therefore be prohibited from using the lane from 10 p.m. to 6 a.m. the following morning every day from November 10 to 30.
The contractor must provide road signs, barriers, delineator posts, signal lights and lighting, and assign staff to guide vehicles and regulate traffic at the work zone. Construction will take place at night, and the lane must be cleared and reopened before 6 a.m. each morning.
Drivers are advised to watch for road signs, follow traffic controllers' instructions and reduce speed when passing the work zone.
The Ho Chi Minh City–Trung Lương–Mỹ Thuận Expressway expansion project is 96.13 km long and has a total investment of more than VND36.1 trillion. It is being carried out without state-budget funding.
Under the plan, the Ho Chi Minh City–Trung Lương section will be expanded to eight lanes with a design speed of 120 km/h. The Trung Lương–Mỹ Thuận section and the stretch from the An Thái Trung interchange to the northern end of Mỹ Thuận 2 Bridge will be completed with six lanes and a design speed of 100 km/h.
Across the construction site, contractors have deployed about 450 machines and pieces of equipment, 1,400 workers and 69 work teams. The completed work is valued at more than VND2.8 trillion.