On November 10, Nghe An Chairman Vo Trong Hai inspected the waste-to-energy plant site in Hai Loc commune with provincial Vice Chairman Bui Thanh An and leaders of relevant departments. The project investor is Galax, a company in the AMACCAO ecosystem.

Construction reaches about 35% after nearly three months
The plant has total investment of VND4.056 trillion. It is designed to process 1,500 tonnes of household waste a day and generate 30 MW of electricity. The plant will use Martin mechanical grate technology from Germany.
The emissions system is designed to meet European standard 2010/75/EU. Monitoring data will be sent online to regulators and published on the plant's portal. It is the largest waste-to-energy project under construction in central Vietnam.

The investor's representative said construction was about 35% complete nearly three months after the August 19 groundbreaking ceremony. The main equipment has been ordered and paid for, and the first shipment is expected to arrive at the site in November 2026.
Under the adjusted investment plan, phase one is scheduled for completion in the fourth quarter of 2028 and phase two in the fourth quarter of 2030. Galax has nevertheless committed to bringing both phases into operation in the fourth quarter of 2027.
Authorities identify three issues for the plant
After hearing the investor's report and proposals, the provincial chairman assigned agencies to resolve three issues that will affect the plant's launch after construction is completed.
First, the plant needs a waste supply. The Department of Agriculture and Environment must work with the Department of Finance, local authorities and other agencies to prepare a waste-routing plan, secure the supply, set a pricing mechanism and arrange waste-treatment service contracts. It must report to the provincial People's Committee by November 25.
Second, the Southeast Economic Zone Management Board was ordered to speed up appraisal of the proposed 110 kV transmission-line project and submit it for investor approval in accordance with regulations.
Third, the Southeast Economic Zone Management Board must work with relevant agencies to complete procedures and build a pumping station and raw-water pipeline. These facilities must be completed together with the plant.
The chairman also told Galax to focus resources on construction, equipment installation, auxiliary works and operating conditions. The company must bring the entire project into operation in the fourth quarter of 2027, as committed.
Investor proposals must be handled within 10 working days
The chairman ordered the agriculture and environment, finance, and industry and trade departments, the Southeast Economic Zone Management Board and other agencies to review, guide and resolve requests from local authorities and the investor within 10 working days of receiving them.
The Southeast Economic Zone Management Board will monitor the assignments and report difficulties and matters beyond its authority to the provincial People's Committee.
Province plans centralized household-waste treatment
The plant is being built at the Nghi Yen solid-waste treatment complex, which has faced heavy pressure from landfill use and environmental problems affecting nearby residents for years. The provincial People's Committee has assigned the Department of Agriculture and Environment to prepare a waste-routing plan and pricing mechanism. The plan is intended to send Nghe An's household waste for centralized incineration and power generation at the project.
With capacity of 1,500 tonnes a day, the plant is expected to reduce household-waste landfill use in the province and add electricity to the national grid.
The company representative said the investor had committed resources to the schedule while authorities had issued specific assignments with deadlines and responsible agencies. The company said the AMACCAO project in Nghe An has the basis to operate as planned.
Sources: Dân Trí