Cao Lanh speeds up embankment construction after Tien River landslide

Cao Lanh in Dong Thap is speeding up construction of an embankment along the Tien River. The project is scheduled for completion in December 2026.

Embankment construction on the Tien River in Cao Lanh
Photo: Thanh Niên

More than a year after a severe landslide, construction of an embankment along the Tien River on Nguyen Huong Street in Dong Thap is being accelerated. The project is expected to be completed in December 2026.

On November 9, contractors continued urgent work to repair the riverbank along Nguyen Huong Street in Cao Lanh, Dong Thap. The project is intended to protect property and help stabilize residents' lives in the area.

Nguyen Cong Bang, the project supervisor at Regional Investment and Construction Project Management Board No. 1, said contractors resumed work after a clear site was handed over and focused on sections that had fallen behind schedule.

The project is now about 86% complete. Four work teams, totaling about 50 workers, are on site. Workers are also operating at night to speed up construction. Railings and lighting equipment have been delivered for installation.

About 80 meters of the main embankment structure remain to be built, Bang said. This section is expected to be completed by the end of November. Contractors will then finish the remaining work, including installing sand beams, laying sidewalk tiles, tiling flower beds and installing railings. The entire project is expected to be completed in December.

Earlier, on September 20 and 24, 2025, a severe landslide occurred along this section of Nguyen Huong Street. Heavy rain and rapidly rising floodwaters coincided with heavy river traffic in the area.

Embankment work after the landslide in Cao Lanh

The landslide stretched for about 500 meters, and in some places reached 30 to 70 meters inland. It affected 35 households, or 132 people, while many homes and plots of land collapsed into the river.

In addition to the section already affected, about 1,600 meters of riverbank was identified as at risk of further landslides. About 285 households, or more than 900 people, could be affected.

Tien River bank being reinforced after the landslide

In October 2025, the Dong Thap provincial People's Committee ordered the construction of an emergency project to address the landslide along the Tien River near Nguyen Huong Street.

The project covers a dangerous section about 520 meters long, including the embankment's end sections. It is funded by the provincial budget and other lawful sources. Regional Investment and Construction Project Management Board No. 1 was appointed as the investor.