Businesses reported delays to infrastructure projects at a meeting held by the Long Son authorities in Ho Chi Minh City on November 10. They said the delays were affecting investment, production and business activity.
Infrastructure projects behind schedule
A representative of Long Son International Port asked about the schedule for the road to Naval Region 2 and the Long Son–Cai Mep road. The two routes are intended to improve cargo transport and connections for production and business in the area.
The company asked the local authorities to provide a 2027 plan for the road to Naval Region 2. If funding has not yet been allocated, it also wanted to know when work could begin. For the Long Son–Cai Mep road, businesses asked when the route was expected to open because the project is behind schedule.
Nguyen Trong Thuy, chairman of the Long Son People's Committee, said the road to Naval Region 2 already exists and is partly in use. The Naval Region 2 Command built it to serve the naval base and Brigade 167.
The road has not been handed over to local authorities after several years of operation. After assessing the situation, the commune decided that widening it was necessary for the area's development and proposed a four-lane road.
"Long Son is working with the Naval Region 2 Command on handing the road over to the local authorities. Ho Chi Minh City is proposing funding. The current plan is to clear the site in 2027 and start construction in 2028," Thuy said.
The Long Son–Cai Mep road is being developed by the provincial project management authority for transport and specialized agricultural projects in Ba Ria–Vung Tau. It was initially scheduled to open in December 2025, but construction delays moved the target to December 2026.
The commune's leaders said local authorities had repeatedly asked the relevant agencies to speed up the work and would continue to seek completion under the revised schedule.

Representatives of the Long Son oil and gas industrial zone also asked when the Long Son resettlement area would be handed over. Its schedule directly affects land acquisition and site clearance for new projects.
Thuy said the Long Son oil and gas industrial zone includes plans for a large-scale No. 3 oil refinery and an underground storage facility. He said the project would significantly affect local residents, so the authorities planned to support businesses and residents while following regulations.
The Long Son resettlement area covers about 60 hectares and is being developed in three phases. It is now largely complete for site clearance and related projects.
Long Son's development potential
Businesses also proposed creating a Long Son Business Association to share information and improve cooperation among organizations operating in the area.

The commune chairman said the proposal came from the business community itself. Local authorities support the association and will help with the process of mobilizing members, organizing its first congress and enabling members to share information.
Long Son's leaders said the area has development opportunities through links with Can Gio, Phu My and other parts of Ho Chi Minh City's emerging growth zone. In its long-term planning, Long Son is considered an important area in the city's development strategy for the next 100 years.
The area is gradually preparing basic infrastructure for that development. Truong Sa and Hoang Sa roads are largely complete under the planning direction. Work is also under way on electricity, VNPT and Viettel telecommunications networks, land matters and site clearance.
Long Son still has delayed infrastructure projects and unresolved issues. At the same time, the area has large industrial, energy, urban and transport projects in its plans. Businesses want more than updates on individual schedules: they are also asking for concrete measures to remove obstacles, improve the investment environment and give local companies a role in the economic chain.