The Ho Chi Minh City Department of Construction sent VEC a request to ensure traffic safety on Truong Luu Street in Long Truong Ward during the expansion of the Ho Chi Minh City - Long Thanh expressway. If trucks continue to carry mud onto city roads, the authorities may withdraw permission for vehicles carrying equipment and materials to use them.
According to the department, the project investor is the Southern Expressway Projects Management Unit, or SEPMU, which belongs to VEC. Construction has caused numerous problems affecting traffic safety on Truong Luu and Tam Da streets.
Material trucks regularly dragged mud onto the road, putting local residents at risk. The construction company continued to leave the problem unresolved despite repeated warnings. Mud kept covering the carriageway, causing serious traffic hazards and environmental pollution.
The Department of Construction asked VEC to direct SEPMU to correct the situation. If the problems continue, the department will consider withdrawing the document that allows trucks carrying equipment, supplies and construction materials to use roads managed by the city.
The department's specialised inspection unit was also assigned to work with the traffic police and Ho Chi Minh City police to inspect Truong Luu Street and take strict action over unsafe construction practices. It must report the results by November 20.
The Centre for Transport and Technical Infrastructure Management was tasked with studying and proposing a solution to flooding on the street. It must report to the Technical Infrastructure Division by November 30.
Earlier, on November 9, the Long Truong Ward People's Committee reported that a roughly 300-metre section of Truong Luu Street, from the elevated Ho Chi Minh City - Long Thanh - Dau Giay expressway toward Nguyen Duy Trinh Street, was frequently damaged. The road had many potholes and mud, creating a risk of accidents and polluting the surrounding area.
Local authorities had repeatedly inspected the section with the Centre for Transport and Technical Infrastructure Management, issued reminders and requested repairs. The damaged road surface continued to recur, however, leading to further complaints and petitions from residents.
Water also remains on the section between house numbers 28 and 39 for long periods after rain, and the problem has not been fully addressed.

The ward People's Committee asked the Department of Construction, the investor and the contractor to fully repair the damaged road surface, potholes, mud and spilled materials. The contractor must also clean and repair the affected roads regularly and restore them to their original condition.
Sources: Dân Trí