Hanoi approves major expansion of urban railway network

Hanoi's People's Council approved special mechanisms to accelerate construction of five urban railway lines covering a combined 253km by 2030.

Urban transport in Hanoi
Vietnam News

Hanoi's People's Council on Wednesday approved a resolution introducing special investment mechanisms to accelerate construction of five urban railway lines, as the city seeks to develop a modern public transport network by 2030.

The five lines, Nos. 1, 2, 8, 10 and 14, will cover a combined 253km and be built under turnkey contracts, People's Committee Chairman Vu Dai Thang told the council.

Total investment in Hanoi's urban railway network during 2026-2030 is expected to exceed VND1 quadrillion (US$38.9 billion), including about VND900 trillion (US$35 billion) for the five lines.

The city plans to mobilise funding from its own budget, central government support, official development assistance loans, bond issuance and revenue from land development around public transport hubs under the transit-oriented development (TOD) model.

Thang said the city would impose strict cost controls, including a contract ceiling of US$120 million per kilometre for underground sections, excluding certain costs outside the contractual scope.

Authorities will also tighten oversight of advance payments to ensure that funds are used solely for their intended purposes and are not diverted to other projects or contractors' private business activities.

Main contractors will be accountable for construction quality, progress and investment efficiency. The city will strengthen supervision throughout the project cycle, from design and technology selection to construction and commissioning.

The resolution also requires technology transfer and training for engineers, technical staff and railway operations and maintenance personnel to take place alongside construction.

Vice chairman of the municipal People's Committee Truong Viet Dung said revisions to the draft had clarified the respective responsibilities of investment decision-makers, project owners and strategic contractors.

The draft removed a proposed requirement for contractors to demonstrate minimum financial resources of VND60 trillion. Instead, they must prove their financial capacity and ability to arrange funding in accordance with regulations.

Other revisions strengthened provisions on advance payment guarantees, contract performance bonds, cash-flow management and price adjustments.

People's Council Chairwoman Phung Thi Hong Ha said the resolution would provide a basis for accelerating the five projects, easing traffic congestion and supporting Hanoi's long-term urban development.

She urged the municipal government to promptly establish implementation plans, assign clear responsibilities and deadlines, and strengthen oversight to prevent delays, financial losses and waste.

Sources: Viet Nam News