A bridge without approach roads has been built on the Bien Hoa–Vung Tau Expressway

The central span of a bridge linking the Bien Hoa–Vung Tau Expressway with the DT 770B road in Dong Nai is complete. Its 550 metres of approach roads have not been built because the required land has not been cleared.

A concrete bridge span over the Bien Hoa–Vung Tau Expressway in Dong Nai
Photo by Dân trí

The Bien Hoa–Vung Tau Expressway opened to traffic on 29 April. However, the bridge intended to connect it with the DT 770B road in Phuoc Thai Commune, Dong Nai City, has remained unfinished for about six months.

The concrete span crosses the expressway, but there are still no approach roads. Drivers have seen the structure since the road opened.

Concrete bridge span over the Bien Hoa–Vung Tau Expressway without approach roads

The design calls for a five-span main bridge measuring 220 metres. One span over the expressway is complete, while two approach spans on each side are still under construction.

A representative of Project Management Board 85, the investor for Component 2 of the Bien Hoa–Vung Tau Expressway, said the contractor was accelerating work and planned to finish the main bridge this year.

The two approach roads, with a combined length of 550 metres, have not been built because the site is not available. The area contains gardens and a few houses.

Workers finishing a bridge pier on the Bien Hoa–Vung Tau Expressway

At the site, workers are finishing the bridge piers, pouring concrete for the pier caps and preparing to install the beams. One row of houses has already been demolished to clear space for the piers.

The investor said the main facilities in Component 2, including 18.2 kilometres of the main route and three major interchanges, had been completed. The bridge at the expressway's junction with DT 770B remains unfinished because land for the approach roads has not been handed over.

The Ministry of Construction recently proposed handing the approach-road work to Dong Nai City for completion with local funds. Dong Nai City has asked the ministry to continue work on both the bridge and the approach roads.

The DT 770B road is intended to connect the city's northern and eastern areas with National Highway 51, expressways and Long Thanh Airport. It begins at the DT 763 road in Xuan Bac Commune and ends at National Highway 51 in Phuoc Thai Commune.

A review report by the National Assembly's Economic and Financial Committee said the Bien Hoa–Vung Tau Expressway could not yet be operated as an integrated route because the DT 770B overpass and other related facilities were affected by unresolved land clearance.

The committee said that if the unfinished approach roads are transferred to local authorities, the legal basis, funding source and responsibility of the receiving party must be clearly defined. This is intended to prevent gaps in responsibility and preserve the project's integration.

Sources: Dân Trí